Invoicing for extra work and variations: get it agreed, then get it paid

Invoicing rules · Published 28 November 2026 · Updated 16 November 2026 · 5 min read

Quick answer: get every change to the original job agreed in writing before you do it, price it separately, and show it as its own line on the invoice with a reference to the agreement. Extra work that's only discussed on site is the most common reason a final invoice gets disputed. Here's a simple process and the sums.

Make your invoice in a minute

Try it freeMake an invoice now, no sign-up. Then 14 days free, then £1.99 a month or £19.99 a year.Trade invoice templates: find yours
On this page
  1. What a variation is
  2. Step 1: Agree it before you do it
  3. Step 2: Price it separately
  4. Worked example: a kitchen job with two extras
  5. Step 3: Show it on the invoice
  6. If you charge VAT
  7. What if nothing was agreed?
  8. A habit that saves arguments

Checked against GOV.UK and legislation.gov.uk on 16 November 2026. General information for UK sole traders and subcontractors, not legal advice.

What a variation is

A variation (also called extras, a change order or additional work) is anything that changes the job after the price was agreed: an extra socket, a bigger patio, a wall that turns out to need replastering, or a Saturday you weren't expecting. It might add cost, remove cost or change the timetable.

Variations are normal. The trouble starts when the customer thinks "while you're here" was free and you thought it was extra.

Step 1: Agree it before you do it

For anything beyond a few pounds, stop and confirm four things:

  • What the extra work is.
  • How much: a fixed price, or an hourly or day rate with an estimate.
  • Materials: who buys them and whether they're included.
  • Time: whether the finish date moves.

Then put it in writing. A text or email is enough for a small job: "Hi Mrs Khan, just confirming the extra downlights in the hallway are £180 labour plus materials at cost, on top of the agreed £2,400. OK to go ahead?" A "yes" reply is your record. For larger jobs, use a short variation form or a revised quote.

The law helps if you don't. The Consumer Rights Act 2015, section 51, says that if a consumer contract doesn't fix a price or say how it's fixed, the consumer pays a reasonable price, and what's reasonable is a question of fact. That's a weaker position than a clear written price, and you may find yourself arguing about what's reasonable.

Step 2: Price it separately

Don't bury extras in the main price. Keep the original contract price, then list each variation with its own amount. You can show the running total so the customer isn't surprised.

Worked example: a kitchen job with two extras

Lee, a sole trader, agrees to fit a kitchen for £3,200 labour. Part-way through, the customer asks for two extras, and one planned item isn't needed. Lee isn't VAT registered.

ItemHow agreedAmount
Kitchen fitting, original agreementQuote dated 2 Nov£3,200.00
Variation 1: move sink pipeworkEmail 12 Nov, 6 hours at £35£210.00
Variation 2: extra wall unitsText 13 Nov, fixed price£95.00
Variation 3: no splashback fitted (removed)Email 13 Nov−£120.00
Total labour£3,385.00
Less deposit already paidInvoice 1−£800.00
Balance due£2,585.00

The sums: 6 × £35 = £210.00; £3,200 + £210 + £95 − £120 = £3,385.00; £3,385 − £800 = £2,585.00. Because each change names the date and how it was agreed, the customer can see exactly why the price moved. See deposits and stage payments for how to show payments already made.

Step 3: Show it on the invoice

  • Keep the original price as the first line and each variation as a separate line.
  • Add the date and form of agreement ("email 12 Nov") so it can be checked.
  • List materials separately from labour. This matters under CIS, where deductions apply to labour but not to materials the subcontractor paid for. See how to invoice for materials.
  • Show credits (items removed) as negative lines or a reduction, so the total adds up.
  • Include everything GOV.UK says an invoice needs: a unique number, your name or business name, the customer's name and address, a clear description, the supply date, the invoice date and the amount.

If you charge VAT

If you're VAT registered, the extra work carries VAT like the rest of the job at the rate that applies to it. Show net, VAT and gross clearly. Variations can change the VAT rate or whether the domestic reverse charge applies if the nature of the work changes, so check each extra rather than assuming it follows the main job.

What if nothing was agreed?

  • Be honest about the gap. If you did extra work on a verbal "go on then", say when and what was said. Invoice it at the rate you'd normally use and be ready to compromise.
  • Never add surprise extras to a final invoice without explaining them first. Send a message that goes through them before the invoice arrives.
  • Treat disputes calmly. See what to do if a client disputes an invoice.
  • For business clients, the same clarity helps with late payment: statutory interest and fixed recovery costs depend on a clear due date and a clear amount owed.

A habit that saves arguments

Keep a one-line "variations log" for each job: date, what, price, how agreed. It takes a minute and turns the final invoice into a copy of the log.

How BillMyWeek helps: you can add extra lines to an invoice with a description, hours or amount and a note, mark materials separately for CIS, and turn a saved quote into a draft invoice. It doesn't track variations or make credit notes, so keep your own log and list each change as its own line. You can try it without signing up; it's a 14-day free trial, then £1.99/month or £19.99/year.

Free: The UK Contractor's Cheat Sheet 2026/27

CIS rates, overtime maths, tax dates, mileage, VAT and late payment, on 2 pages. Keep it on your phone or print it for the van.

We'll email you the cheat sheet. Unsubscribe any time. Tips only if you tick the box. Privacy

Frequently asked questions

Can I charge for extra work the customer asked for verbally?

You can, but it's harder to prove. Price it reasonably, explain what was said and when, and agree changes in writing next time.

Should variations be on the same invoice or separate?

Either works. Many people list them as separate lines on the final invoice, each with the date it was agreed, so the total reconciles to the original price.

What if the customer refuses to pay for extras?

Go back to what was agreed in writing. If a price was never agreed, a consumer only has to pay a reasonable price, which is a question of fact.

Do variations change the VAT?

If you're VAT registered, VAT applies to the extra work at the rate that fits it, so check each item.

Sources

This guide is general information, not legal, tax or financial advice. Rules and rates change, so check the linked GOV.UK pages for the current position.

Make this week's invoice in a minute

BillMyWeek fills in your days, day rate and overtime, takes CIS off labour if you need it, and gives you a clean PDF to send. 14 days free, then £1.99 a month or £19.99 a year. No card needed to start.

Try it free: make an invoice now, no sign-up Start your free trial

Free tools

Day rate calculatorDay rate to hourly, overtime and weekend ratesCIS deduction calculatorTake-home after 20%, 30% or 0% CISAnnual income calculatorDay rate to weekly, monthly and yearly incomeOvertime calculatorTime and a quarter, half and double timeTime and a half calculatorHourly and day rate at x1.5Overtime tax calculatorEstimate tax and NI on overtimeLate payment interest calculatorStatutory interest and fixed compensationVAT calculatorAdd or remove VAT, with the construction reverse chargeSelf-employed tax calculatorIncome Tax, Class 4 NI and take-home for 2026/27CIS refund calculatorEstimate your CIS tax refund or billMileage allowance calculatorHMRC 55p and 25p rates for 2026/27Markup and margin calculatorPrice materials and jobs, convert markup to marginHoliday pay calculator12.07% holiday pay and day rate time offFree quote generatorLabour and materials quote with VAT and CIS, saved as a PDFFree invoice chaserPayment reminder messages for text, WhatsApp and emailEtsy fee calculatorEtsy UK fees, VAT and profit per saleeBay fee calculatorPrivate and business seller fees and profitVinted tax checkerHobby or trading, HMRC reporting and taxSide hustle tax calculator£1,000 trading allowance and tax on top of a jobWorking from home expensesHMRC flat rates and 55p mileageDelivery driver tax calculatorMileage and tax for couriersAmazon seller fee calculatorReferral, plan and FBA feesRent a Room calculator£7,500 tax-free lodger incomeContractor's cheat sheet 2026/27CIS, overtime, tax dates, mileage, VAT and late payment on 2 pagesCIS cheat sheetOne-page PDF for subcontractorsIs my invoice legal? checkerCheck an invoice against GOV.UK requirementsFree invoice templatesInvoice, quote, CIS statement and day-rate templatesSample invoiceSee a finished weekly invoice PDF, no sign-up

Start a free BillMyWeek trial to turn your numbers into a ready-to-send invoice.